Onondaga County Department of Transportation

Buckley Road Pavement Resurfacing Project

P.I.N. 3755.78

Project Description

This project will include asphalt pavement resurfacing of a portion of Buckley Road from the Morgan Road intersection to the intersection with Henry Clay Boulevard in the Town of Clay, Onondaga County, New York. The total project length is 0.95 miles. In addition, select areas of the existing shoulders will be repaired. The project will also include: cleaning and repairs to the existing roadside drainage system, repairs to the existing flush concrete medians at each intersection, updates to the traffic signal equipment at the Morgan Road intersection, new pavement markings over the resurfaced roadway and improvements to the roadway signage and existing guide railing system as necessary. Construction is anticipated to begin and be completed in 2018.

Buckley Road
Buckley Road

Location Map

Project Facts

Additional Right-of-Way

No Property Acquisitions will be needed for this project.

Pedestrian and Bicycle Access

Pedestrian and bicycle access will be maintained along Buckley Road during construction.

Work Zone Traffic Control

Vehicular traffic will be maintained on Buckley Road at all times for the construction project. At certain times during construction, traffic will be controlled by construction flaggers that will alternate the direction of traffic that can proceed around the work area while the other direction of traffic is stopped. Driveways will be accessible during the construction period.

Anticipated Costs

Total project cost: $1,090,000.

This is a Federally Funded, Locally Administered, Federal Aid Project. Anticipated Funding sources are 80% Federal, 15% State, and 5% County.

Key Project Dates

Design Approval: March 2017

Construction Start: Anticipated April 2018

Construction Completion: Anticipated October 2018

Questions / Comments

Please send any questions or comments you have by March 3, 2017.